Mass flowmeter Installation, Adjustment and Operation - Just Measure it

Mass flowmeter Installation, Adjustment and Operation

Installation of meters

The mass flow meter mostly is divided into two parts: a sensor (primary meter)

and a transmitter (secondary meter), a shielded cable connects two parts. The transmitter(secondary meter) of the essential safety flow meter must mount in the safety area according to prescriptive conditions (see section 3.2). A sensor and a transmitter of the essential safety flow meter installation show in Figure 4.

Figure 4 Sketch of Essential Safety Flow Meter Installation

The transmitter (secondary meter) of the essential safety flow meter normally

fixes at a cabinet. Drill a square hatch 152mm X 152mm on the panel of the cabinet; install the transmitter with attached securing plates, nuts, and screws referring to Figure 5.

Figure 5 Essential Safety Transmitter Installations

The transmitter (secondary meter) of composite type mounts on the sensor

(primary meter) with attached screws. A shielded cable connects two parts.

Installation of the sensor shows in Figure 6, illuminate hereinafter now:

(1) The mass flow meter normally installs in a level line, the main body

perpendicularly downwards. PLS pay attention to the direction label on the flow meter, which should be the same as the direction of the fluid in the line. If can not confirm direction, PLS see

Figure 6 and 10, while the cable socket on the back of the mass flow meter, the flow direction is from left to right;

(2) Securing supports should be built-in upper and lower reaches of a line

besides the flow meter;

(3) Ensure concentric with two flanges of flow meter and line while

installation. When screwing, screws should be forced uniformity symmetrically, do

not impose contraposition, forbidden wring or bend the primary meter;

(4) Definite back pressure should keep in the lower reaches of a line behind

flow meter. Do not let line direct open, prevent incorrectly measure while a half tube of liquid;

(5) The sensor (primary meter) must leave up ground, and do not touch anything;

(6) The tube of the upper reaches of the line must equal or large than the meter’s

inner diameter, forbidden to less than;

(7) The body of the sensor should be covered with heat preserved material, for

measuring the liquid that easily gasifies. Or, the sensor may be damaged with frost or dew;

(8) For the type of DN1, DN3, DN6, and DN10, the sensor should install on

ground, use the soft tube to connect to the lines;

(9) The serial number of the sensor and transmitter should same if the serial

number not match, the error may be bigger than normal;

5.2 Conditions required for installation

To guarantee the accuracy, conditions required when installation should be met,

because the mass flow meter is a high precision instrument:

(1) The sensor (primary meter) and the transmitter (secondary meter) do not

install in a strong magnetic interferential area. Or, measuring signals would be disturbed, and debase the accuracy;

(2) There is must not any other vibrator on line installed the sensor (primary

meter);

(3) If install outside of the door, PLS pay attention to circumstance temperature not to exceed the range of the meter, and should consider building a weatherproof shield to avoid blowing and drenching, for increasing lifetime of the flow meter.

(4) The transmitter (secondary meter) of essential safety should mount in safety

area or appropriate control room.

(5) A shielded cable with ten core lines connects the sensor (primary meter) and the

transmitter (secondary meter) of essential safety.

The output cable of the transmitter (secondary meter) of the composite is a shield

cable with ten core lines.

Five meters long of the cable is a normal option in the package by our company.

Customs can deal with special orders for a longer cable, but not exceed 200 meters.

Dimensions

Dimensions Table

Specs Line Sizes
(mm)
Fitting Options (mm) Number and Hole Diameter of
Flange join or
Screw join (mm)
Weight
KG
A B C D
DN1 1 193 200 75 234 M12×1.5 Screw join 4
DN3 3 193 225 75 288 M12×1.5 Screw join 4.5
DN6 6 214 234 69 328 M16×1.5 Screw join 7.5
DN10 10 256 291 73 370 M20×1.5 Screw join 9
DN15 15 413 503 90 φ65 4-φ14 15
DN25 25 473 548 96 φ85 4-φ14 18.5
DN40 40 522 613 116 φ110 4-φ18 25.5
DN50 50 597 676 137 φ125 4-φ18 35
DN80 80 650 837 175 φ160 8-φ18 53.5
DN100 100 714 934 198 φ190 8-φ22 70
DN150 150 815 1123 265 φ250 8-φ26 85